In the project for the construction of the Erdenes Tavantolgoi JSC coal beneficiation plant in Tsogtsetsii sum, Umnugobi province, our company's team of over 60 specialists successfully completed the electrical quality control and repair work. Within the scope of this project:
- 0.4kV, 10kV distrubution substations
- Steam boiler, Fine particle section
- Main coal beneficiation plant
- Screening and crushing plant
- Enclosed coal storage facilities
- Enclosed concentrate storage facilities
- Power coal storage, Repair center
- Wagon and truck loading/unloading station
- Flotation, storage & laboratory sampling sections
and 15 facilities of the industrial complex, including:
- Electric motor - 692
- Grounding frames - 36
- Control panels - 934
- 10kV distribution substation - 3
- 10kV distribution substation - 7
- Automation equipment - 221
- Control cable lines - 2224
- power cable lines - 1110
for which measurements, tests and technical document validation work were carried out and successfully handed over to the State Commission.